A network planning technique for the analysis of a projects completion time used for planning and controlling the activities in a project. By showing each of these activities and their associated times, the critical path, which identifies those elements that actually constrain the total time for the project, can be determined. See: critical chain method, network analysis, critical activity, critical path.
关键路线法—分析项目完工时间的网络规划技术,用来规划和控制项目活动。通过显示每一项活动及其相关时间,就能够确定关键路线,它标识出实际约束项目总时间的那些要素。参见:critical chain method,network nanlysis.